Zonda 50MW Wind Farm

The project refers to the construction of a 50MW Wind Farm, consisting of 9 wind turbines with 5.5MW each and a 60 / 30kV substation for connection to the grid.

QUADRANTE had full responsibility for the Environmental Studies and Engineering Design regarding all disciplines (earthworks-access roads and wind turbine platforms, structures- foundations of Wind Turbines and Civil Construction Substation, geotechnics, hydraulic, electric, etc).